BACKGROUND
Mayor and Members of the Town Council
Department of Public Works
Recommendation Approve a Change Order to the Stewart Drive Storm Drain
Rehabilitation. Project. — URGENCY ITEM
The Stewart Drive Storm Drain Rehabilitation Project includes pipe rehabilitation and replacement
work for the storm drain system on Stewart Drive between Sonora Court and Tiburon Boulevard, and
Silverado Drive. The construction of the project was included in the 2015/16 Capital
Improvement Plan and funded in the amount of $500,000 including contingency and soft costs.
The project was designed by Harrison Engineering Inc to include a base bid and an alternate bid.
The difference between these options is lining two pipe segments rather than replacing them. The
lining option saved considerable money and based on older videos supplied by the Town it
appeared lining was a feasible option for these lines. The low bid for the project with the lining
was $323,100, much lower than the bid for replacing all the lines at $430,470. On July 1, 2015,
Council awarded the project Cratus Inc. for $323,100.00 plus a 15% contingency. At the same
time Council awarded a construction management contract bringing the total budget for the
project to $419,951, under the $500,000 in the CIP budget.
On August 17, 2015, we received the video inspection done by the contractor prior to lining.
This video indicated severe deterioration has occurred since the Town's last video of these line
segments. It is impracticable to line these pipes; the amount of repairs that would be needed to
make the pipes suitable for lining would result in a total cost greater than outright replacement.
Replacing the lines will add $108,000 to the contract cost. In addition, the revised project with
contingency would exceed the amount budgeted in the CIP for this project.
ANALYSIS
The pipes are significantly deteriorated and need to be replaced. The Contractor has started work
and is scheduled to replace the storm drains between through August 28, 2015, with final paving
and cleanup occurring by September 4, 2015.
Waiting until the next Council meeting to decide on this issue would expose the town to claims
from the contractor for delays or additional extra work and potentially expose the Town to a
breach of contract claim. We also note that we have two contractors trying to work in this area
TOWN OF TIBURON PAGE 1 OF 2
Town Council Meeting
August 19, 2015
and coordinate schedules. An uncertain schedule for on contractor could result in delay claims
from the other contractor.
FINANCIAL IMPACT
The 2015/16 Capital Improvement plan included funding in the amount of $500,000 including for
construction, construction contingency and construction management. This change will increase
the required funding to about $527,000. Note that the overage is less than the contingency in this
project. Therefore staff recommends that Council allow staff to use funds currently budgeted for
storm drain flushing as needed to cover the contingency on this project. Funding is from the
Street Impact Fund and Gas Tax.
RECOMMENDATION
Staff recommends that the Town Council:
1. Approve a motion by two-thirds vote that places this item as an urgency item on the
agenda by finding that there is a need to take immediate action and that the need for that
action came to the attention of the Town subsequent to the agenda being posted.
2. Approve a change in the contract price of $107,370 for the Stewart Drive Storm Drain
Rehabilitation Project.
3. Approve a motion that allows staff to draw on funds in the CIP for the Storm Drain
Flushing Project to cover contingencies as needed for the Stewart Drive Storm Drain
Rehabilitation Project.
Prepared by: Patrick Barnes, Director of Public Works
TOWN OF TIBURON PAGE 2 OF 2
Current
With Change
Order
Construction
$323,100
$430,470
Contingency
$48,465
$48,465
Total Construction
$373,581
$480,951
Design
CM
$45,980
$45,980
Total
$419,561
$526,931
RECOMMENDATION
Staff recommends that the Town Council:
1. Approve a motion by two-thirds vote that places this item as an urgency item on the
agenda by finding that there is a need to take immediate action and that the need for that
action came to the attention of the Town subsequent to the agenda being posted.
2. Approve a change in the contract price of $107,370 for the Stewart Drive Storm Drain
Rehabilitation Project.
3. Approve a motion that allows staff to draw on funds in the CIP for the Storm Drain
Flushing Project to cover contingencies as needed for the Stewart Drive Storm Drain
Rehabilitation Project.
Prepared by: Patrick Barnes, Director of Public Works
TOWN OF TIBURON PAGE 2 OF 2