Loading...
HomeMy WebLinkAboutAgr 2006-03-30 (Reed/Madden) Town of Tiburon STAFF REPORT AGENDA ITEM -----Z- ... .............. ..... .......................... TO: Mayor and Members of the Town Council Heidi Bigall, Interim Town Manager <td- FROM: SUBJECT: Approve Changes to Scope of Work - Fountain Art Project April 5, 2006 REVIEWED BY: 1:f MEETING DATE: ........................ ............ ............... The contract agreement between the Town of Tiburon and the artists for the fountain art project requires that any material changes in the scope of work be submitted to the Town. The Town then has five working days to approve said changes. The attached Exhibit "E" details proposed changes to the original contract and was submitted to the Town on March 30, 2006. These changes have been reviewed by the Director of Public Works/Town Engineer, Councilmember Berger and Laleh Zelinsky and they recommend approval. These changes do not result in any increase to the contract price. Recommendation It is recommended that Council approve the proposed changes to the Scope of Work for the Fountain Art Project and that the attached exhibit be incorporated into the oriQinal AQreement. 9 Exhibit Revised Scope of Work, dated 3/30/06 2dct fv v".4t q I?- A-M- " ~~ ~~ '1~)>O~ EXHIBIT E-Revision Revised Scope of Work 3/30/06 Sculptural Fountain "Coming About" The following items in bold represent changes to the original Scope of Work as shown below. Reed Madden Designs will provide the following: · Work schedule and payment plan · Construction drawings for city permit with structural engineering by Jacob Feldman. (City will waive any permit fees.) · Schematic pump and fountain specifications by fountain engineer - Goepp Associates. Fountain engineer is now George Forni of Aquatic Environments. · Donor plaque purchase and installation with dedication per Town Funding Agreement with Laleh Zelinsky Donor plaque location has been changed to a seven-foot bronze strip within the fountain edge. · Title plaque purchase and installation with title, date and artists names · Plumbing and electrical hookup from city services to vault and fountain. (Town will provide water, sewer and electrical hook ups to site or will reimburse artist for cost of this work) · Vault excavation, installation and plaza resurfacing for vault hookup. (Resurfacing for main water and electrical lines done by the city) · Demolition and removal of existing circular-tiered planter · Construction and installation of fountain sculpture containing: Seven Sail-Tail kinetic sculptural elements in orbital-brushed stainless steel Sculpture is now five (5) sails to reduce visual crowding and potential bumping of sails in high winds. Pool: approximately 22-foot diameter, max. 18" deep Depth of pool in upper basin is to be 3" deep Two approx. 12-foot infinity water edges with grating and trough for catchments. One 52-foot continuous infinity edge with grating and trough. (Doubles the size of the waterfall and corresponding pumps/filters as well as basin and stainless steel grating). FO,untain is now 700 gallons per minute versus original 300 gpm. Boat-wall & bench (colored concrete with stainless steel suspension rods) 8' Lens-shaped bench (colored concrete) Benches are now made out of stainless steel with colored concrete inserts for increased visual interest and skateboard resistance. Single arc bench on pool edge (colored concrete) (Eliminated to be replaced with bronze water weir) Walking surface between "boat" benches (colored concrete w/groves every 2") 3' x 55' Perimeter concrete surface with seeded rock for anti-skateboarding. Perimeter is to be increased to 4.5' wide with sand-lapping concrete pattern. * 50' concrete or stainless-steel curb to deter leaf litter in water catchment. 6/28/05 · Install waterworks & lighting components Adjustable Low Profile Underwater Lights (minimum 16) 24 lights are now proposed due to increase in fountain size. Electrical-Plumbing Vault by Fountain People, Inc. (or equivalent other) containing all controls, recirculation pumps, ozone filtration, and water treatment systems. Features include: Heavy-duty FRP enclosure, structurally engineered and certified for in-ground installation; full electrical clearance per NEC standards; thermally protected pumps; forced air ventilation system; automatic sump pumps, interior heavy-duty light fixtures; OSHA approved fiberglass ladder; non-skid rubber floor mat; lockable lid with lock-open arm, stainless steellock hasp, and stainless steel hinge; stainless steel anchors and tie-down cables; main pump strainers; 18" sand filter with multi-port valve; 1"-2" water fill station (Auto Fill) with solenoid valve, pressure reducing valve, water hammer arrestor, and hose bib with hose. W all mounted maintenance procedures for all equipment. Vault is no longer the above described prefab fiberglass unit by Fountain People. Custom concrete vault with individual components will be constructed by Reed Madden and Aquatic Environments. (Fiberglass unit is not appropriate in high-water table conditions. Custom components are preferable.) . Plaza resurfacing around perimeter to restore plaza to pre-work condition Other additions and changes to Scope of Work include the following: -Addition of an Anemometer (to shut off fountain in high winds) set 12' high near PG&E meter and stop sign and connected to fountain vault. - Addition of two skimmers set on either end of the lower catchment basin (each:::: 10" round and high to catch leaves for easy clean out). - Addition of strip lighting along the inner edge of both "boat" benches. Note: *Proposed concrete surface texture for skateboard and slip resistance should be approved by city. Samples are available for review. 6/28/05 S:J/;? ~.Ik c{ 00 ;fl'/Z vI- (:; {jr r / () " '7 c /;{J( if ' _. Ik cl ~ t!!rJ"J ~ /-t \ r-- )}~ ;// 0 V , f' LI~).,c .M Fr. Town ofTiburon · 1505 Tiburon Boulevard · Tiburon, CA 94920 · P. 415.435,7373 F. 415.435,2438 · www.ci.tiburon.ca.us Office of the Town Clerk / 415,735.7377 September 9, 2005 1tt;ff ,,------ Y--3/,-OJ Jeffrey Reed and Jennifer Madden Reed Madden Designs 1014 Curtis Street Albany, CA 94706 SUBJECT: AGREEMENT FOR COMMISSION OF PUBLIC ART WORK Dear Mr. Reed and Ms. Madden: Enclosed is your duplicate, signed copy of the above agreement. Thank you for your cooperation in this matter. Vf~)t}2~~ ' Diane Crane lacopi Town Clerk Enclosure Cc: Town Manager Director of Public Works AGREEMENT FOR COMMISSION OF PUBLIC ART WORK ~r THIS AGREEMENT is entered into thisSl day of August, 2005, by and between the Town of Tiburon, a municipal corporation (hereinafter "Town"), and Jeffrey Reed and Jennifer Madden, doing business as Reed Madden Designs (hereinafter collectively, "Artist"). RECITALS 1, The Town owns a plaza area located at the intersection of Main Street and Tiburon Boulevard in downtown Tiburon ("Site"), which the Town has long intended as the site for a public art project incorporating a fountain. The Town Council has appointed an ad hoc Committee to lead the consideration of potential projects. 2. On June 12, 2004, the Town issued a Request for Qualifications to artists that might be interested and qualified to create a fountain art project for the Site. The Committee reviewed the responses and, on July 5, 2004, sent a Request for Proposals (Exhibit A, "Artwork RFP"), to four of the artists that had submitted their qualifications, asking them to submit proposals for the design, fabrication and installation of artwork in accordance with the specifications in the proposal package dated for the Fountain Plaza Art Project. Three artists submitted proposals in response to the Artwork RFP. 3. The Artist submitted a proposal consisting of the following items: (a) a model, presently on display in the Town Council Chambers, which is depicted in Exhibit B; (b) a written description (Exhibit C); and drawings (Exhibit D) (collectively, "Artist Proposal"). The Artist Proposal represented that the total cost of the Artwork described therein would be Two Hundred Fifty Thousand Dollars ($250,000). 1 4. The Town's ad hoc committee forwarded the Artist's Proposal to the Town Council for consideration, together with two other proposals. The Town Council heard the three artists' presentation of their proposals on January 5, 2005. On February 2, 2005, the Town Council hear selected the Artist's Proposal as recommended by ad hoc committee; and 5, Artist is a recognized professional artist, and the Town is sufficiently familiar with the style and quality of the Artist's work to desire the Artist to create and install the Artwork described in the Artist's Proposal ("Artwork") for location at the Fountain Plaza, at the intersection of Tiburon Boulevard and Main Street, in Tiburon ("the Site"). NOW, THEREFORE, the Town and the Artist, for the consideration and under the conditions hereinafter set forth, agree as follows: ARTICLE 1: SCOPE OF SERVICES 1-1 GENERAL (a) Except as otherwise expressly provide in this Agreement, the Artist shall perform all services and furnish all supplies, materials, artist and agent travel, and equipment as necessary for the design, execution, fabrication, transportation, and installation of the Artwork at the Site, as set forth in the Artist Proposal and the Scope of Work (Exhibit E), (b) The Artwork RFP provides that the Town shall be responsible for bringing utilities to the Site as provided in the Artwork RFP, including electrical power, water and sanitary sewer connection. The Town may elect to have the Artist perform this work, to be reimbursed at the Artist's cost. 2 1-2 THE ARTWORK (a) Within 90 days of the execution of this Agreement, Artist will provide a written description and technical specifications of the Artwork, including the documents listed below, for review and approval by the Town's Director of Public Works ("Director"). Upon the Director's approval, these documents will be incorporated into this Agreement. · Graphic rendering; · Draft Maintenance and Conservation Form; · Work plan and Production Schedule; · Proposed list of subcontractors (those known to date); · Other information about the Work as may be reasonably required by the Town in order to certify the compliance of the Work with applicable statutes and ordinances. Said exhibits will become the property of the Town upon submission by the Artist. Upon request by Artist, the Town shall promptly furnish all available exhibits in connection with said submission at the artist's expense. (b) Upon approval by the Town Council and written direction to move forward, the Artist shall commence with fabrication at their studio and transportation and installation of the Artwork at the Site. (c) Artist will upgrade the originally proposed sand filtration system to an ozone filtration system as referenced in the Scope of Work for an additional cost of Three Thousand Five Hundred Dollars ($3500). (d) This project is funded by a gift from Laleh and Miriam Zelinsky (collectively, "Zelinsky") in honor of the late Edward Zelinsky pursuant to an agreement between the Town and Zelinsky dated July 20, 2005 ("Funding Agreement"). Artist will incorporate memorial text into the Artwork as set forth in Paragraph 3 of the Funding Agreement. 3 (e) The Town may require the Artist to make such revisions to the proposed Artwork as are necessary for the Artwork to comply with applicable statutes, ordinances, or regulations governing the project, including, without limitation, the Americans with Disabilities Act, or for other practical (non-aesthetic) reasons. Without limiting the forgoing, the Director must review and approve all surfaces that could be walked upon for slip resistance. (f) The Artist fee may be equitably adjusted for any increase or decrease in the Artist's cost of, or time required for, performance of any revisions pursuant to this Section 1-2. The Artist must present any claim for adjustment under this paragraph, including the amount thereof, to the Town in writing as soon as practicable, but in no event more than ten (10) days after receiving the revision. . (g) Within thirty (30) days after receipt of the Artist's revisions, pursuant to this Section 1-2, the Town shall notify the Artist of its approval or disapproval of such revisions, The Town may require the Artist to submit additional revisions until such revisions are accepted by the Town. Revisions made and accepted by the Town pursuant to this Section 1-2 become a part of the final design, technical specifications and fabrication and installation schedule of the Artwork. 1-3 EXECUTION OF THE WORK (a) Pursuant to Section 1-2 above, the Artist shall commence fabrication of the Artwork, in accordance with the Project Schedule set forth in Exhibit F. The Artist shall perform all of the obligations under this contract on or before June 1, 2006. 4 (b) The Town shall have the right to review the Artwork at reasonable times during the fabrication. The Artist shall submit to the Town bi-monthly progress reports in accordance with the Project Schedule. (c) The Artist shall complete the fabrication and installation of the Artwork in substantial conformity with the approved Proposal. (d) The Artist shall present to the Town, in writing, for further review, any "significant changes" in the scope, design, color, size, material, or texture of the Artwork not permitted by or not in substantial conformity with the Proposal. A "significant change" is: 1. Any material change in the scope, design, color, size, material, texture, operating or moving elements or location of the Artwork on the Site; ii. Any material change in the Artwork that affects installation, scheduling, site preparation, or maintenance for the Artwork; or 111. Any change in the concept of the Artwork as represented in the accepted proposal, (e) T own will review and approve or disapprove any submission within 5 business days of submission, If changes reviewed by the Town are not approved, the Artist will not resume the Artwork nor resume the payment schedule until changes to the Artwork are reviewed and approved by the Town. 1-4 DELIVERY AND INSTALLATION: LIOUIDATED DAMAGES 5 (a) Prior to commencement of work at the Site, the Artist shall notify the Town of schedules for installation. The Artist shall be responsible for all expenses and labor. The Town will waive all permit fees. (b) Prior to delivery of the Artwork, the Artist shall notify the Town in writing when fabrication of the Artwork is completed and the Artist is ready for delivery of the Artwork to the Site. ( c) The Artist shall provide for completion of the Artwork in compliance with appropriate codes and the Project Schedule. Without limiting the foregoing, all work on Town property shall comply with the Town's normal conditions for encroachment permits, attached as Exhibit G. The Director shall have authority to waive any conditions that he finds are inapplicable to this project. (d) The parties have agreed to a Completion Date of June 1, 2006. In the event that the Artist is unable to complete the Artwork by the Completion Date because of unexpected heavy rains, natural disaster, or serious illness, Artist shall so notify the Town at least eight (8) weeks in advance of the Completion Date and request an extension of up to 30 days, which request the Town shall not unreasonably deny. (e) The Parties acknowledge that time is of the essence in this Agreement and wish to avoid the cost, difficulty and delay of proving the damages caused by delay. Accordingly, the Parties agree that for each calendar day's delay beyond the Completion Date of June 1, 2006, or any extension thereof granted by the Town pursuant to this section, Artist shall forfeit and pay to the Town as liquidated damages $100 per day for each of the first six days (i.e., June 7, 6 2006, if there is no extension); $200 per day for each of the next seven days (i.e., June 14, 2006 if there is no extension); $300 per day for the next seven days (i.e." through June 21, 2006 if there is no extension); $400 per day for the next 7 seven days (i.e., through June 28, 2006 if there is no extension); and $500 per day each day thereafter (i.e., after July 5, 2006 if there is no TOWN 1-5 POST INSTALLATION (a) Within thirty (30) days after the installation of the Artwork, the Artist shall furnish the Town with the following documentation of the Artwork as installed: 1. One set of digital photographs of the completed Artwork, one taken from each of three different view points; ii. The Town shall have the right to duplicate and distribute for any noncommercial purpose the artwork documentation supplied by the Artist under this Agreement; 111. The Artist shall be available at such time or times as may be agreed between Town and Artist to attend any inauguration or dedication ceremonies relating to the transfer of The Artwork to the Town. The Town shall use its best efforts to arrange for publicity for the completed work in such art publications and 7 otherwise as may be determined between the Town and the Artist as soon as is practical following installation. IV. All warranties for materials, equipment and other materials for the Artwork (b) Upon completion and before final project acceptance by the Town, the Artist shall provide the Town with written instructions for appropriate maintenance and preservation of the Artwork. 1-6 FINAL ACCEPTANCE (a) The Artist shall advise the Town in writing when all services required under this Agreement have been completed in substantial conformity with this Agreement. (b) The Town shall notify the Artist in writing of the fmal acceptance (or non- acceptance) of the Artwork, (c) Final acceptance shall be effective as of the earlier of the following dates: I. The date of the Town's notice of final acceptance; or 11. The 30th day after the Artist has sent written notice to the Town required under Section 1-6(a) unless the Town, upon receipt of such 3D-day notice and prior to the expir.ation of the 3D-day period, gives the Artist written notice specifying and describing the services, which have not been completed, 1-7 RISK OF LOSS The risk of loss or damage to the Artwork shall be borne by the Artist until final acceptance, and the Artist shall take such measures as are necessary to protect the 8 Artwork from loss or damages until final acceptance, Notwithstanding the forgoing, After the Artist has given the Town the notice specified in Section 1-6 (a), the Town shall be responsible for any damage to the Artwork resulting from impact from a motor vehicle. 1-8 INDEMNITY The Town has commissioned Artist to construct a fountain sculpture to be designed and built in a highly used public space, The Town recognizes and accepts the inherent risk associated with a project of this nature, and this project in particular. However, the Artist is responsible for the design, fabrication and installation of the Artwork. This section shall control the parties respective responsibilities for any liability, claim or other loss or damages, (a) The Artwork consists of the following elements: · Seven Sail-Tail kinetic sculptural elements in orbital-brushed stainless steel · Pool: approximately 22-foot diameter, max. 18" deep · Two approx, 12-foot infinity water edges with grating and trough for catchments. · Boat-wall & bench (colored concrete with stainless steel suspension rods) · 8' Lens-shaped bench (colored concrete) · Single arc bench on pool edge ( colored concrete) · Walking surface between "boat" benches (colored concrete w/groves every 2") · 3' x 55' Perimeter concrete surface with seeded rock for anti- skateboarding, · 50' concrete or stainless-steel cub to deter leaf litter in water catchment. (b) The Artist shall indemnify, defend and hold the Town and its officials, employees, and! or agents harmless from any and all claims or liabilities then existing or arising thereafter from the Artist's negligence or willful 9 misconduct in designing, fabricating and installing the Seven Sail-Tail kinetic sculptural elements. (c) The Town shall review the building construction and material selection to meet its safety concerns and shall indemnify the Artist from any and all liability that does not arise from Artist's negligence or willful misconduct in designing, fabricating and installing the Seven Sail-Tail kinetic sculptural elements. 1-9 TITLE.. ASSIGNMENT OF ROYALTY RIGHTS.. AND WAIVER (a) Title to the Artwork shall pass to the Town upon final acceptance, The Artist hereby assigns the right to collect any royalty payment provided by Civil Code section 986(a) to the Town and to the Town's assigns. Town shall have the right to use Artist's name, likeness and biographical information in connection with the display or reproduction and distribution of the Artwork, including, without limitation, all advertising and promotional materials concerning the Town or the Artwork, (b) Except as expressly provided below, the Town shall not intentionally damage, alter, modify, or change the Artwork without the prior written consent of the Artist. (c) The Artist acknowledges and agrees that the Town may require the Site for purposes other than the display of the Artwork, The Town agrees that it will notify the Artist of any proposed alteration of the Site that would require the removal or relocation of the Artwork or affect the intended character and appearance of the Artwork and will consult with the Artist in the planning and 10 execution of any such removal, relocation, or alteration and will make a reasonable effort to maintain the integrity of the Artwork, (d) The Artist acknowledges and agrees that the Town retains the right to relocate or remove the Artwork from public display for any reason, at the sole discretion of the Town, Reasons for removing the Artwork from public display shall include, but not be limited to: hazards to public health, safety or welfare; unsightly or deteriorated conditions of the Artwork; or the need to access, repair and maintain public facilities, ( e) Except as provided above, the Artist expressly waives, for himself and his successors in interest, to the greatest extent allowed by law, any rights he or she may have under California Civil Code sections 986, 987, 988 and 989, ARTICLE 2: COMPENSATION AND PAYMENT SCHEDULE 2-1 AGREEMENT AMOUNT AND PAYMENT (a) The Artist's compensation under this Agreement shall not exceed TWO HUNDRED FIFTY-THREE THOUSAND, FIVE HUNDRED DOLLARS ($253,500), which will constitute full compensation and payment for all services to be performed under this Agreement including artists' fees, execution, fabrication, artist and/or agent travel, transportation, and installation. (b) Except as provided by laws governing emergency procedures, officers and employees of Town are not authorized to request, and the Town is not required to reimburse Artist for, commodities or services beyond the scope of this Agreement unless the changed scope is authorized by amendment and approved as required by law. Officers and employees of Town are not authorized to offer or promise, 11 nor is Town required to honor, any offered or promised additional funding in excess of the maximum amount of funding for this Agreement without amendment of the Agreement. THIS SECTION CONTROLS AGAINST ANY AND ALL OTHER PROVISIONS OF THIS AGREEMENT. (c) Town shall make payments according to the Project Schedule. (d) All requests for payment shall be submitted to the Director in writing for review and approval and must be accompanied by a detailed invoice and original receipts and other documentation as required by the Director regarding the work completed. (e) Payment shall be issued within 30 days of approval of detailed invoices and requests for payment by the Director, 2-2 ARTIST'S EXPENSES The Artist shall be the sole responsible party for all mailing or shipping charges on submissions to the Town, and the costs of all travel by the Artist and the Artist's agents and employees necessary for the proper performance of the services required under this Agreement. ARTICLE 3: WARRANTIES 3-1 WARRANTIES OF TITLE The Artist represents and warrants that: (a) The Artwork is solely the result of artistic effort of the Artist; (b) Except as otherwise disclosed in writing to the Town, the Artwork is unique and original and does not infringe upon any copyright; 12 (c) That the Artwork, or a duplicate thereof, has not been accepted for sale elsewhere; and (d) The Artwork is free and clear of any liens or claims from any source whatsoever. 3-2 WARRANTIES OF QUALITY AND CONDITION The Artist represents and warrants that: (a) The execution and fabrication of the Artwork will be performed in a professional manner (expert, qualified, skilled); (c) The Artwork, as designed, fabricated and installed, (i) will be free from any defects in materials and workmanship; (ii) is suitable to withstand without cracking, chipping, pealing, facing, rusting or otherwise deteriorating, the climactic and environmental conditions commonly experience within and in the general vicinity of the Town of Tiburon; and (iii) is durable, taking into consideration that the Site is an unsecured public space that may be exposed to elements such as weather, temperature variation and considerable movement of people and equipment. ; and (d) Reasonable maintenance of the Artwork will not require procedures substantially in excess of those described in the maintenance recommendations by the Artist to the Town; (e) The warranties described in this Section 3-2 shall survive for a period of five (5) years after final acceptance of the Artwork. The Town shall give notice to the Artist of any observed breach with reasonable promptness. The Artist shall, at the instruction of the Town, and at no cost to the Town, cure reasonably and 13 promptly the breach of any such warranty which is curable by the Artist and which cure is consistent with professional standards, including for example, cure by means of repair or re- fabrication of the Artwork as determined by the Town. (f) Any warranty on this project is void if damage is due to invasive roots from trees, plantings, or any other changes to the existing area beyond the Artist's control. The Town has been advised by the Artist that the existing plaza Ficus Trees in particular, pose a risk for uplifting pipes, vault and pool. The Town assumes all risk to the project by these trees. 3-3 WARRANTIES OF ARTWORK The Artist represents and warrants that the Artwork will not substantially vary or deviate from the Town approved Artwork without the prior written consent of the Town. ARTICLE 4: INSURANCE 4.1 Contractor shall provide and maintain insurance as set forth in this Article on behalf of Town. ( a) Commercial General Liability Insurance (primary) shall be provided on ISO-CGL form No, CG 00 01 .11 85 or 88. or equivalent. Policy limits shall be no less than one million dollars per occurrence for all coverages and two million dollars general aggregate. Town and its employees and agents shall be added as additional insured using ISO form CG 7057 (03-96) or equivalent. Coverage shall apply on a primary, non-contributing basis in relation to any other insurance or self-insurance, primary or excess, available to Town or any employee or agent of Town. Coverage shall not be limited to the vicarious liability or supervisory 14 role of any additional insured, Coverage shall contain no contractors- limitation endorsement. There shall be no endorsement or modification limiting the scope of coverage for liability arising from pollution, explosion, collapse, underground property damage or employment-related practices. (b) Business Auto Coverage shall be written on ISO Business Auto Coverage from CA 00 01 06 92 or equivalent including symbol 1 (Any Auto). Limits shall be no less than one million dollars per accident. This policy shall be scheduled as underlying insurance to any umbrella policy required above for a total limit of no less than two million dollars each accident. (c) Workers Compensation/Employers Liability: Artist shall provide workers compensation statutory benefits as required by law. Employers liability limits shall be no less than one million dollars per accident or disease. Employers liability coverage shall be scheduled under any umbrella policy described above. Unless otherwise agreed, this policy shall be endorsed to waive any right of subrogation as respects the Owner. 4.2 Before commencement of any work at the site, the Artist shall secure all insurance required under this Article and provide written proof to the Town Attorney, nor shall the Artist allow any subcontractor to commence work on any subcontract until the subcontractor has obtained similar insurance submitted proof thereof to the Town Attorney. ARTICLE 5: COPYRIGHT 5-1 Copyright in the Artwork and related design, drawings, sketches, and models will be owned by the Artist until acceptance of the Artist's Artwork by the Town 15 pursuant to Section 1-6 hereof. Notwithstanding the foregoing, the Artist agrees not to make use of such copyright in the Artwork for any purpose other than the performance by the Artist of the Artist's obligations under this Artwork Agreement, without the written consent of the Town, Upon acceptance of the Artist's Artwork pursuant to Section 1-6 hereof, copyright in the Artwork will be owned jointly by the Town and the Artist. Except as expressly authorized by this Agreement, no use of the copyright will be made by the Artist or the Town without the written consent of the other, which consent will not be unreasonably withheld. 5-2 The Artist certifies that the Artwork is a unique work of art especially designed for the Town, and shall not duplicate or reproduce the Artwork nor shall the Artist permit others to do so except with the written permission of the Town. 5-3 The Town has the right to reproduce and distribute in printed form and on commercial documents and or brochures or any other literature of the Town, photographs, realistic renderings, videotapes, or films of the Artwork. Such reproductions and use of the images of the Artwork for promotional purposes shall not constitute a breach of copyright and no royalty shall be due and payable by the Town to the Artist for such use. 5-4 The Artist has the right to reproduce and distribute in printed form and on commercial documents and or brochures or any other literature of the Artist, photographs, realistic renderings, videotapes, or films of the Artwork, Such reproductions and use of the images of the Artwork for promotional purposes, including any authorized books by the Artist, shall not constitute a breach of 16 including any authorized books by the Artist, shall not constitute a breach of copyright and no royalty shall be due and payable to the Town for such use. 5-5 CREDIT TO THE ARTIST All reproductions of the Artwork by the Town shall contain a credit to the Artist. 5-6 CREDIT TO THE TOWN The Artist shall use his best effort to give a credit in any public showing under the Artist's control of illustrations of the Artwork to the Town. ARTICLE 6: ARTIST'S RIGHTS 6-1 MAINTENANCE The Town shall reasonably protect and maintain the Artwork against the ravages of time, vandalism, skate boarders and the elements, in accord with the instructions of the Artist provided under Section 1-5(b). 6-2 ARTIST REPRODUCTION RIGHTS Pursuant to Article 5, Section 5-1, the Town agrees that the Artist shall have the right to reproduce and distribute in printed form and on non-commercial educational materials and brochures advertising or promoting the Artist and the Artist's career, two-dimensional images such as photos, slides or realistic renderings, video tapes, or films of the Artwork as installed and formally accepted by the Town. Such reproductions and use of the images of the Artwork for promotional and educational purposes shall be deemed to not constitute a breach of copyright in any way and no royalty fee shall be due and payable to the Town for such use. Such reproduction and images of the Artwork for publicity, 17 promotion, and educational purposes shall, to the extent reasonably possible and appropriate, give reference to the Town of Tiburon. ARTICLE 7: ARTIST AS INDEPENDENT CONTRACTOR The Artist shall perform all work under this Agreement as an independent contractor and not as an agent or employee of the Town. The Artist shall not be supervised by any employee or official of the Town nor shall the Artist exercise supervision over any employee or official of the Town, The Town alerts the Artist to the provisions of the Labor Code ~ 1771, which may require the payment of prevailing wages. ARTICLE 8: ASSIGNMENT. TRANSFER AND SUBCONTRACTING Neither the Town nor the Artist shall assign or transfer any interest except through inheritance in this Agreement without prior written consent of the other. The Artist may subcontract portions of the services to be provided hereunder at the Artist's expense provided that said subcontracting shall not affect the design, appearance or visual quality of the Artwork and shall be carried out under the personal supervision of the Artist, and in accordance with all applicable laws. ARTICLE 9: TERMINATION If either party to this Agreement shall willfully or negligently fail to fulfill, in a timely or proper manner, or otherwise violate any of the covenants or agreements material to this Agreement, then the other party shall thereupon have the right to terminate this Agreement by giving written notice to the defaulting party of its intent to terminate, specifying the grounds for termination. The defaulting party shall have ten (10) days after receipt of the notice to cure the default. In the event of default by the Artist, all finished and unfinished drawings, sketches, photographs, and other products prepared 18 and submitted or prepared for submission by the Artist under this Agreement shall, at the Town's option, become Town property, This, however, shall not relieve the Artist of liability to the Town for damages sustained by the Town by virtue of any breach of this Agreement by the Artist. In addition to all other remedies, the Town may reasonably withhold payments to the Artist until such time as the exact amount of damages due the Town from the Artist is determined. ARTICLE 10: CONTRACT ADMINISTRATOR The Contract Administrator for this Agreement shall be the Director or his or her designee. ARTICLE 11: NONDISCRIMINATION In carrying out the performance of the services designated, the Artist shall not discriminate as to race, religion, sex, age, sexual orientation, national origin, the presence of any physical, mental or sensory handicap, or any other basis prohibited by applicable law. ARTICLE 12: COMPLIANCE The Artist shall be required to comply with all federal and state laws and Town statutes, ordinances, and regulations applicable to the performance of the Artist's services under this Agreement ARTICLE 13: ENTIRE AGREEMENT This writing embodies the entire agreement and understanding between the parties hereto, and there are no other agreements or understandings, oral or written, with reference to the subject matter hereof that are not merged herein and superseded hereby. 19 ARTICLE 14: MODIFICATION No alteration, change, amendment, or modification of the term of this Agreement shall be valid, unless made in writing and signed by both parties hereto and approved by appropriate action of the Town. ARTICLEI5:~AIVER No waiver of performance by either party shall be construed as or operate as a waiver of any subsequent default of any terms, covenants, or conditions in this Agreement. The payment or acceptance of fees for any period after a default shall not be deemed a waiver of any right nor an acceptance of performance. ARTICLE 16: GOVERNING LA~: VENUE The laws of the State of California shall govern this Agreement, regardless of where executed or performed. The County of Marin shall be the venue for resolving any disputes arising out of this Agreement. ARTICLE 17: HEIRS AND ASSIGNS This Agreement shall be binding upon and shall inure to the benefit of the Town and of the Artist and of their respective heirs, personal representatives, successors, and permitted assigns. ARTICLE 18: NOTICES All notices, requests, demands, and other communications which are required or permitted to be given under this Agreement shall be in writing and shall be deemed to have been duly given upon delivery and receipt thereof, as the case may be, if delivered personally or sent by certified mail, return receipt requested, postage-prepaid as follows: 20 Town: Director of Public Works Town of Tiburon 1505 Tiburon Boulevard Tiburon, CA 94920 Artist: Jeffrey Reed and Jennifer Madden Reed Madden Designs 1014 Curtis Street Albany, CA 94706 ARTICLE 19: ATTORNEY'S FEES Should any action or proceeding be brought to enforce the terms of this Agreement, the prevailing party shall be entitled to reasonable attorney's fees and costs. ARTICLE 20: EXHIBITS This Agreement includes the following Exhibits, which are attached hereto and incorporated herein by reference: Exhibit A Exhibit B Exhibit C Exhibit D Exhibit E Exhibit F Exhibit G Artwork RFP Artwork Model Artwork Description Artwork Drawings Scope of Work Project Schedule Encroachment Permit Conditions 21 IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed by his respective authorized officers or representatives as of the day and year set forth on page one of this Agreement. TOWN CLERK APPROVED AS TO FORM: --7~~ TOWN ATTORNEY TO ARTIST g/>lbs 22 EXHIBIT NO.A- A CIVIC FOUNTAINJOB TIBURON CALIFORNIA REQUEST FOR QUALlFICA liONS July 5, 2004 Reed Madden Designs 3944 lime Avenue Long Beach, CA 90807 Dear Mr. Reed and Ms, Madden, As discussed in our phone conversation, on behalf of the Tiburon Town Council, and 0 Committee of Tiburon and Belvedere Gtizens, we are pleased to ask you to submit your qualifications to be considered for the commission of a civic fountain for downtown Tiburon, CA. The fountain will occupy the most prominent location in historic downtown nburon. It is intended to provide 0 . gathering place for our citizens and guests and memorable thematic imagery through the ioyful animation of water, light and movement. With this letter we have induded: CJ 1" = 20' plan of the site CJ 1" = 20' aerial photograph of the s~e CJ a site photograph CJ Fountain Proied Parameters - Outline of parameters and characteristics for the fountain. The Process for awarding the commission and executing the proiect are outlined as follows: CJ Request for Qualifications [RFQ] sent by Tiburon July 15, 2004 CJ RFQs returned by artists August 15, 2004 CJ Selection of [up to four] finalists to be asked to submit Conceptual Designs September 15, 2004 The conceptual design will be represented by drawings, a written description of the design and its water operation, lighting and other features and materials as appropriate, a photo montage of the design in place, and a model at a scale of no less than 1/2" = l' - 0". The conceptual design will also be accompanied by a cost estimate by the artist and licensed building contractor. The artists selected to prepare the Conceptual Design will receive an honorarium of $5,000 upon the presentation of the Design. CJ Presentation of Conceptual Design to Committee November 15, 2004 CJ Public Presentation of the Conceptual Designs to the Town Council November 20, 2004 CJ Designs Remain on Public Display November -December , 2004 CJ Council will announce its selection of the design to be awarded the commission .December 1 , 2004 During the fundraising period and through the completion and dedication of the 'fountain the Conceptual Design Presentation materials will remain in the possession of the Town of nburon for its use. [J After fundraising, the commission for the work will begin. The Town of Tiburon Building Deportment and Public Works Deportment will receive engineering and building permit applications. Fees will be waived by the Town of Tiburon. Upon receipt of building permits, the artist and his/her contractors may begin work. [J Completion is anticipated nine months after the commission is awarded. The Request for Qualification [RFQ] should include the following: (J Artist's vita, commissions, awards and publications os appropriate. Particularly important will be information about other public art proiects and fountains. [J The artist will be responsible for the entire proied. The artist will assemble and direct the team of fabricators, engineers, suppliers and builders to complete the entire proiect. A written description of the process os envisioned by the artist and the names and qualifications of the other members of the artist's -team should be included. Q A portfolio of the artist's relevant work. This will remain with the Town of nburon until the selection of the finalists or if selected as a finalist, then until the award of the commission. It will then be returned to the artist. if requested. Q The names and contacts of references from other communities or individuak who hove commissioned similar proiects from the artist Q The artist's agreement in principal to the process as discussed in this letter. The Committee would also be interested in the artist's comments and suggestions regarding amendment of the process. No preliminary design for this commission is required for the RFQ Please address your RFQ package to: Mr. Pat Echols Director of Public Works/T own Engineer - Town of nburon nburon Town Hall 1505 nburon Blvd. Tiburon, CA 94920 We ore sending the RFQ to a limited number of artists (fewer than 10). We ore very excited to begin the process of design and construction of the town fountain proiect. We hove received much public support and expressions of financial participation for the fountain and we look forward to working . with you. Sincerely, VV1!\ Miles Berger - Vice Mayor , To u on (c Tom Gram, Alice Fredericks, Alex Mcintyre, Pat Echols b> FOUNTAIN PROJECT PARAMETERS July 5, 2004 o THE PROJEaWILl BE A FOUNTAIN WITH WATER USED IN SOME FORM. AS THE LOCATION IS SUBJEaTO OCCASIONAL WINDY DA YS,CARE WILL BE TAKEN IN THE DESIGN TO UMIT WIND.BLOWN SPRAY. o THE FOUNTAIN SHOULD CONTAIN A SCULPTURAL ELEMENT IN METAL, STONE, MOSAIC, OR ANY MATERIAL THAT WORKS WITH THE ARTlm CONCEPT. [J THE ELEMENTS ARE TO BE FIGURATIVE WITH A ClEAR THEME UNIQUE TO TlBURON AND TO THE LOCAL HISTORY OR SBTING. THEMATIC ELEMENTS MAY INCLUDE: o TIBURON'S NAMESAKE SHARK CJ THE RAILROAD HISTORY OF THIS lOCATION o SAILING o OTHER FIGURES OR ELEMENTS FROM TlBURON HISTORY [J OTHER APPROPRIATE THEMES SUGGESTED BY THE ARTIST [J THE EXISTING ARfA OF THE EXISTING CONCRETE PODIUM OR "WEDDING CAKE" PLANTER Will BE THE SITE AND LOCATION OF THE WORK, THE EXISTING PODIUM CAN BE REPLACED OR ENCASED IN NEW MATERIALS THAT SHOULD COMPUMENT OR MAY BEA FEATURE OF THE NEWPROJEa. [J THE FOUNTAIN IS TO BE A GATHERING POINT WITH A SEATING ELEMENT, THE SEATING MAY BE A PART OF THE PODIUM OR AROUND IT AS A PART OF THE WORK. [J THE DESIGN SHOULD BE SAFE FOR FAMILY'S NORMAL REASONABLE USE, [J THE EXISTING TREES ARE TO SAY AND THE REMAINDER OF THE PLAZA IS TO REMAIN "AS IS". [J THE FOUNTAIN SHOULD INCORPORATE LIGHT OR BE LIT [AS PART OF THE OVERAll BUDGET] TO BE ATIRAOlVE AT NIGHT AS WELL AS DURING THE DAY [J THE FOUNTAIN EQUIPMENT Will BE OF HIGH QUALITY AND LOW MAINTENANCE, COST OF EQUIPMENT AND UTILITIES WILL BE INCLUDED IN THE BUDGET, [J THE ALL.INCLUSIVE BUDGET SHAll BE S250,000 FOR THE DESIGN, EQUIPMENT, INSTALlATION, UTIUTlES AND FOUNTAIN, THE TOWN OF TIBURON WilL BRING ELECTRICAL AND WATER SERVICE TQ THE SITE. [J THE SCHEDULE IS FOR COMPLETION BY MID 2005. "J\ (f\ () , V\ c:. ~ ~ 11\ Z. ~~ 1\' 1> ~tlJ C) " ~""'<~:~~~'="~" (,.J "{.-v ;, . . . '" ~./ t,/J ".~, "'J,..-~ 'x~ ~1.. ~J (',,!; ":'~<T.; ~- " '. 'l,. :'f.' '1. ,w ,"- c,. "-- ~"'", /::<..J ,. 'V ~';;. "~C_ ~,ii.', "" '". ) 4!0~^, - -7/ " "" v' .... ~ '- '. .;~~ '....-.' '\,. \~ ,(,!'lfo""'" " ~"b1:t.- " / '\~. ~~'~ '" ......~.~. ':-- " '.....1' .......' ~... .x;,. -:. ". V' " /A "_, ~ 'l!::,t'" ",..;. '-, '.~,,' ///' ~'" .... '-." '~~" '\. / . " ~l i ' ... · ,~/(p^" , " '" '" -' /,C' " ~. I __- "- "" ~ <' > ." ',1 : ./" .--,,=-- --. '-. "" - ~ " . i i j)<~~"'_. -_"" ~ · ~ ' ',.'....'\...... ':'!... .\J(~ I ' ,u ,^ ~-... ...<; <""'. ,. h.- .________._...::-::~><I/ ../.....,.'.,.;/jP b~. \. 1(S':~:;yi ~~,..,. K~-'\. ...><~, ~.\..:~;.<(~~~ . . ", ' ,", ,.~ ",.', ,',.. ,.. .';,/ '- '" . -,'- ",,/~.,. ,I 11 ? ",' "\", "-... 'f- "<?" "",\;" y _~~_" ;t-:JMi!J ..__+// ~(~~~ A /,/-~.",\ I' '- C ~,-/' ~ /"~'''-..''' ... (/1 i \' ""~"" y'>'~~ "'i~\ ,,::;::=_.-=-":-"1 \ ,l ~~ ( t \ I I '- '-~" ~i-. '<~ Cl;:;;-::\\ 1___ _ , 0 \ ':!> . I I ",' -- . , ~';;'>, I 1',-, / I '" ~ :..-p."-...~\, ,.,..,"" \ .lL. ~___.../ n"" ;- ~~ ~:... ,1 ". /.1:::: )"'" <1 ,,1> ~ (' , ;-- .. "', -.....p ...-..... i r- "'" '" \ w. 'rci\ + ~"" !- ~ ""'>, "/, ~ r , ..~ r- -' -A '-",,>-. o "'to: 0 I I r- A,a~ .-':;;.. .....:;:~~.:- '- 1+.1 :\" "'. \ ~ 1-1, ., {\ t sf -~>",' \ ~,I. I tG. - f- o+.f ~. . I .~""" . "l. t- #.u':-i '"' 01 ((,0' ' \ . I '" f-'If Ill] ---" ~. \ "' I ' ) I , r - ~... n \ -;;. ('~~ f I I- ~~ ........... ,@) I i- / C, IJ. t '\ '-'7 i I If- IT--F I I o I ~..'C~ t: ~\ I ~ ' " ,~, 10- r- ~ '\i r: .r t= . l.- f r l- I 1-- ~.- /-- .L- -w:.~ ~~ \;:~\J. \ ,''''- r"~- ....... /.... \li-...... ." /( ~ ,.\\ i I ~ \ \ I \ - 1 \ ~..._- -..--.----" _____I \ ~t \ \ ~...., /j i... ":itI.,:"~,, ""/~""~ ';:. t,.-' 't~ ~;:\ ~,u.. ..... '-" ".-- I._I ~ ~ ~ ~ 0- ~ ~ / / I I j I 1 I I ! .. I / {6 ~ ~ :......... ::,~) '\ . ".t, t;. (~ -:~ ,,:;,_ '_J.~ jj ; L..~~~1;:p" ,.....----...-......... ~i r. -., ." ~.) g /-~ - ../....:::~;;k;: ./,/.~.~.1-'" I/;~~:" /l' i /; /" f '.' II J 11 ,If ill III ! ri IJJ j II r l" ~ I,J ~ ""1 ~, , ~r ..,~,. ,~ ..:t.. '\ I I I I (v ~ \ \ \ II \ \ \\ \ II \, \~.. \'\ \ \,~')(t f '- ~~ ~^'" '~~ .~ ~~ - ... 'i, .. ~ < ~'-. -.- If 0'" - '~~ ..... '-:--. ....\.., ~.::~~ .....,.... "'~ ~~" ~ . ~~ N "'....... f:!. -J \ g~ ~g \1&- - - - I I I o N :" r--i .. B (f.) ---- ---- ---- ---- trJ ~ OJ t-4 ~ Z ~ EXHIBIT NO.~ "Coming About" by Jeffrey Reed and Jennifer Madden A shark's fin. A bird's wing. Seven sails glistening above the bay. All of these forms take to life through the graceful rotation of the 12-foot-high, brushed stainless steel sculpture. A shallow reflecting pool below catches the forms above, infusing them with nuanced movement as a gentle flow of water cascades over its infinity- edge. Two benches envelop the pool, evoking the profile of a boat from afar -- its name, "Tiburon," is etched into the starboard hull. Additional seating creates viewing opportunities from multiple angles, giving rise to new forms, born of imagination. The sculpture glimmers at night thanks to indirect lighting within the pool and at its edge, transforming the arching sheets of steel into a beacon for the downtown, both day and night. _t1 2 i' :." Cf .' / i 3 ~! f 1 ..,~:~'~ ,;. ~:'i ,(~)P~~>~ w ~ ~ ~~. 1,1) It; -:::.; '::::~..'" "..... '. ~i. '.. ~; t5 ~ z)O' ~;;,"~ ":~<.",,.~ ,) /~<)~I". ti '/.' , -~ " \" ~~ \ "',--" '" '. f 8 8 '''..\:~>\\ v lJ-.":,~; ;:;~~~r:-:-r'T::i-~::::;;~~1 .~,~~....-C; .' ,..,,~ I _~~~J" }.. '.,' ..,~:, , . ;,/ ' I ~ .... -. .. . , /' "J' I ...~'>.X.: ' - . " , ," ,J r- ',,;v ~ " 7.. '. . ". ',', ~I 1'1,.". I I j c.t"",."" ~'" ", ~ .....:..' ", ,~'- " ./ ;--' 'Tc'\. ':'- '- --x.... '-. ";:. ",. /', ,\:" , , . ' .' ....~. ,.:t tt.. . " ,> /' ,./ \ ,,)...,1 ..",...., -', #.' si>'" ... .... .;-.. . " ,I " ,,'. ..... ,,' .; :'/ '" -" '- " .. ,. . ' ',' I .. ' \ < r '. '.'" .:..' '. / '. ,/ .....,. ....'" .... '.', ..... ..-? " I' . ,.,,' .' .; . .', ' ( , ' / ..t ~ " ) ! /1 ./ (' ~." .' J... . ;/ ~,. "~' ~~~;.\..,....(/ ~~ / // t "7 CO" ./ '~:~)1"::-' ""\ ~...~~"',:' r ~ "'r'(: \.':, '. ' ? .s....... ; '.~~, "", :' -< " '. . '::;:j~i " '~'c. ',.,,: ~ I ,~ ' ~ ILJ . ~:. \ -;;rl :".:. ~,,:,-, '\" :;) . ". .. . ii' . "'" ....- --.'\. <' "'." . ~ .f] '+ ,.' -~ ,..,'" 3 ~;f0' J' L"'- -.---. " ~ ": f-t 1. t;g;.Y t rf:-i', ()/'~"-" ~" /~.::' . -~~~f' "-.~ ':f ~ '.':', f.' ({":" t\ -:'1 <:t r"- . r- ~. 1,:-.:::;) f, -\ .\. I . , ~ ~ ": ~,-".I'" fl. ", '~~,~! .-- ~ / . j'~.~! >':::, i~i"~'-Jjl!~' tr! \;:;.:1 r~~- o')::-\O'i1 i.'Nr . " \." ,. ! ,\ / ' 41 )~..\ fAU ~ ~l: /,.} ../ rr .q, -... ,C':. 0+' y ~~(, ! , I 'I "}_ . . - 1 l' , <'\' I _ 1__,;" iff}; :.. iY\";' ,V . _.. . J L I/f .~ ,I I ~.... ~ Ie" ( ... , .,., .!;f-' ~".; ,f ,')'~ 1"',' \. j . ~$' ( "r .,....; ...ri..... .j' " ,tf. ' . . . " \ '11:')'" \./""" \! v' r I 'i . . . ...~, I' ,(i " '~'.'" " i~ ! . I [ I , ) : I : l , , I , I i I . . J . / , I / I~' ...J ,;....... ~ ~ t-- ~ - ~ I i , i I I ! , i (' ,~.' ' EXHIBIT E Scope of Work Sculptural Fountain "Coming About" The following describes the scope of work to be undertaken by Reed Madden Designs to create a sculptural fountain and seating area for the town of Tiburon. The sculptural fountain will be constructed and scaled as proposed in the model presented to Tiburon Town Council in January, 2005. Reed Madden Designs will provide the following: · Work schedule and payment plan · Construction drawings for city permit with structural engineering by Jacob Feldman. (City will waive any permit fees.) · Schematic pump and fountain specifications by fountain engineer - Goepp Associates. · Donor plaque purchase and installation with dedication per Town Funding Agreement with Laleh Zelinsky · Title plaque purchase and installation with title, date and artists names · Plumbing and electrical hookup from city services to vault and fountain. (Town will provide water, sewer and electrical hook ups to site or will reimburse artist for cost of this work) · Vault excavation, installation and plaza resurfacing for vault hookup. (Resurfacing for main water and electrical lines done by the city) · Demolition and removal of existing circular-tiered planter · Construction and installation of fountain sculpture containing: Seven Sail-Tail kinetic sculptural elements in orbital-brushed stainless steel Pool: approximately 22-foot diameter, max. 18" deep Two approx. 12-foot infinity water edges with grating and trough for catchments, · Boat-wall & bench (colored concrete with st~Iess steel suspension rods) 8' Lens-shaped bench ( colored concrete) Single arc bench on pool edge ( colored concrete) Walking surface between "boat" benches (colored concrete w/groves every 2") 3' x 55' Perimeter concrete surface with seeded rock for anti-skateboarding. 50' concrete or stainless-steel cub to deter leaf litter in water catchment. · Install waterworks & lighting components Adjustable Low Profile Underwater Lights (minimum 16) Electrical-Plumbing Vault by Fountain People, Inc. (or equivalent other) containing all controls, recirculation pumps, ozone filtration, and water treatment systems. Features include: Heavy-duty FRP enclosure, structurally engineered and certified for in-ground installation; full electrical clearance per NEC standards; thermally protected pumps; forced air ventilation system; automatic sump pumps, interior heavy-duty light fixtures; OSHA approved fiberglass ladder; non-skid rubber floor mat; lockable lid with lock-open ann, stainless steel lock hasp, and stainless steel hinge; stainless steel anchors and tie-down cables; main pump strainers; 18" sand filter with multi-port valve; 1"-2" water fill station (Auto Fill) with solenoid valve, pressure reducing valve, water hammer arrestor, and hose bib with hose. W all mounted maintenance procedures for all equipment. · Plaza resurfacing around perimeter to restore plaza to pre-work condition 6/28/05 EXHIBIT F Timing & Payment Schedule Sculptural Fountain "Coming About" Overall budget for project (as outlined in "Scope of Work" document): $253,500 Phase One: (July and August) Complete all design documents and engineering. Phase Two: (September through December) Design development: create prototype mock-up and material samples, test water movement and edge treatments. Phase Three: (January and February) Completion of all off-site fabrication of stainless steel sculptures and mold work. Purchase of fountain equipment and lighting. Phase Four: (March, April and May) Demolition and fountain construction on site. Completion expected by the end of May. Schedule of Payments: $50,700 (twenty percent) upon execution of this Agreement $50,700 (twenty percent) at completion of phase two $76,050 (thirty percent) at completion of phase three $76,050 (thirty percent) at Final Acceptance by Town 6/28/05 ENCROACHMENT PERMIT SPECIAL PROVISIONS Town of Tiburon · 1505 Tiburon Boulevard. Tiburon, CA 94920. P. 435.435,7373 F. 415.435.2438 Office of the Town Engineer / 415.435.7388 LOCATION OF WORK: TIBURON FOUNTAIN PLAZA EXHmIT NO. Gr PERMIT No. Applicant to conform to Special Instructions as indicated below: GENERAL Representative: D D D D D ~ Gf u( [!( ~ u( Altemate: . Applicant must renew permit to perform work after Permit valid until this date. Submit engineer's or contractor's cost estimate for work within public rig ht..o r-way . Fee paid is the minimum fee for this work. Per Town resolution, permit fee is 30/0 of the value of work within the public right-of-way ($300 minimum). Accordingly fee is $ payable before construction begins. A performance bond shall be required in the amount of $ _cash/check Certificate of Deposit Instrument of Credit Bond. Bond shall be Insurance Sidewalk and/or driveway shall be sawcut at existing score lines and the entire section removed and replaced. Permit is for work within the Tiburon public right-of-way and public property only. No work to be done in existing street pavement area. All work shall be done in accordance with the latest APWA Green Book (where applicable). All work shall be done in accordance with the applicable sections of the CalTrans Standard Specifications. All work shall be done in accordance with the latest Marin County Standard Plans and Specifications (where applicable). Before starting work, the applicant shall designate a representative and his/her on-site phone number. The representative shall have complete autQority to act for applicant. An alternate representative may be designated as well. The representative or alternate shall be present at the work site whenever actions of the construction necessitate their presence to protect the work, persons, or property. Any order or communication given to the representative shall be deemed delivered to the applicant. On-site phone number On-site phone number [k( Applicant shall provide Public Works Department with a written work schedule five (5) days prior to scheduled start date. D Applicant shall not begin work on a section unless all previously started sections are either completed or are actively under construction and applicant has the workforce required to start a new section without affecting the progress on previously started sections. S:\Public Works\Engineering Division\Fountain Art Project\E.P. Special Provisions.doc Town ofTiburon. 1505 Tiburon Boulevard. Tiburon, CA 94920. P. 435.435.7373 F. 415.435.2438 Office of the Town Engineer /415.435.7388 [!( ~ Applicant shall protect all trees and landscaping from damage from construction operations. Root pruning and root crown work shall not be performed without the supervision and guidance of the Public Works Department representative. All roots 2 inches in diameter or larger will be examined and preserved. The applicant at no additional cost to the Town shall replace facilities and landscaping in the public right-of-way damaged due to the construction operation, No heavy equipment will be allowed from the face of curb to the property line. Other D D EXCAVATION o All excavation, backfill, and resurfacing must meet (A) Marin County Standard Plan 991, or (B) Town standards, if attached. For trench and resurfacing designs not in conformance with the standard circled above the applicant shall submit engineered drawings to the Town Engineer for approval. o Trenching is not allowed; installation shall be by boring or jacking only. An excavation at. the connection and potholing for obstructions will be allowed. o Open trenches shall not exceed feet at any given time. D Excavations which have not been backfilled permanently by the end of the work period shall be covered with steel plates strong enough to support prevailing traffic. Plate bridging shall be secured against movement. Plates used for bridging shall extend one-foot minimum beyond edges of trench. Temporary paving materials (premix) shall be used to feather the edges of the plates to minimize wheel impacts. o Compaction testing and reports are required for all recompaction of trench fill material. Materials shall be compacted in accordance with the "All Cities and County of Marin, Standard Specifications and Construction Details. II o Backfill shall be Control Density Fill (CDF), or other approved slurry backfill. All slurry backfills shall contain between 200 and 250 pounds of Portland cement per cubic yard of slurry. A mix design for the slurry backfill shall be submitted to the Department of Public Works for review prior to issuance of the permit. o Excavation in this area must be cleared through the Marin County Department of Environmental Health. o No cutback allowed for temporary trench restoration. o Temporary restoration shall be hot mix asphalt ~ Other: Brick pavers and other existina surfaces removed or damaaed durina construction shall be restored to match adiacent surfaces. SURFACE RESTORATION o Pavement must be slurry-sealed to a width exceeding the trench edges by 3' in all directions. o Applicant shall reimburse the Town for its cost to slurry seal the traffic lane or shoulder above the trench. S:\Public Works\Engineering Division\Fountain Art Project\E.P. Special Provisions. doc Town ofTiburon. 1505 Tiburon Boulevard · Tiburon, CA 94920. P. 435.435.7373 F. 415.435.2438 Office of the Town Engineer 1415.435.7388 o A minimum overlay of 2" of A.C. is to be placed in the area of construction to a width of feet. Grinding may be necessary for edge matching. o The traveled way of this street is to receive an overlay of slurry seal through the area of construction. o The applicant, at no additional cost to the Town, shall replace traffic markings removed or damaged due to the construction operation. o Other TRAFFIC CONTROL o Iff' o o rn- o o o [E( o o ~ Submit a complete traffic control plan to the Town Engineer at least five (5) working days prior to the start of construction. Project may be stopped if condition not met. The traffic control plan shall include all streets and locations where work is to be performed and shall indicate each stage of work, closure dates for street and/or lane, section of closure, signage, flagmen and any other pertinent information. The traffic control plan shall be reviewed and approved by the Town Engineer before the contractor shall begin work. Plan shall include which parking spaces will be made unavailable to the public. Coordinate traffic control plan and all temporary road closures with the Tiburon Police Department. Hours of work in street pavement will be limited to Traffic control during construction shall be in accordance with the current edition of the 'Work Area Traffic Control Handbook rNA TCH). Traffic control (if necessary) during construction shall be in accordance with the current CalTrans requirements. At least lane(s) of traffic must be maintained in each direction at all times. Applicant shall make arrangements at their own expense for a staging area for the temporary stockpiling of material and equipment storage. The Contractor will not be allowed to use public streets or property for such purpose without written approval of the Town Engineer. Applicant must notify the Golden Gate Bridge Transit Authority 48 hours prior to the beginning of any work which may interfere with normal bus operations. Emergency access is to be maintained at all times. Charge for use of metered parking Trucks used for the exporting or importing of soil, rock or other granular materials shall be limited to a maximum capacity of six (6) cubic yards. Ready-mix concrete trucks are exempt from this size restriction. Other: Pedestrian access (ADA comoliant) must be maintained around the construction area at all times. S:\Public Works\Engineering Division\Fountain Art Project\E.P. Special Provisions. doc Town ofTiburon. 1505 Tiburon Boulevard · Tiburon, CA 94920. P. 435.435.7373 F. 415.435.2438 Office of the Town Engineer 1415.435.7388 PUBLIC RELATIONS ~ o o ~ ~ o Work shall be accomplished in such a manner as to provide access to all side streets and properties whenever possible. If access to adjacent properties cannot be provided, make direct contact with affected residents/merchants at least 48 hours in advance. Post project limits with notification signs, with contact phone numbers, at least three days before construction, and provide mailer or door hanger, reviewed and approved by the Public Works Department, to affected properties. Where necessary, applicant shall post uNo Parking" signs in areas of work at least seventy- two (72) hours in advance. The signs shall state the day(s), date(s), and time of construction work. uNo Parking" signs shall be placed in full view along the side of the road and not more than one hundred (100) feet apart. In accordance with the Municipal Code, heavy construction noise will not be permitted between the hours of 5:00 PM and 8:00 AM on Monday through Saturday. No work will be allowed on Sundays or holidays. Night work will only be allowed by permission of the Town Engineer. To obtain permission for night work, the permittee shall make a formal request in writing showing the location of properties affected by the disruption of utility service, as well as the properties that will be affected by the construction noise. Work site shall be kept clear and free from rubbish and debris. Clearing sweeping, and sprinkling with water or other means shall be performed to abate dust. The use of water resulting in mud on public streets will not be permitted as a substitute for sweeping or other methods. All cleaning and dust abatement methods must conform to the Best Management Practices (BMPs) guidelines as set forth by the Marin County Stormwater Pollution Prevention Program (MCSTOPPP). Other S:\Public Works\Engineering Division\Fountain Art Project\E.P. Special Provisions.doc