SPECIAL MEETING NOTICE
(Joint Meeting with Belvedere City Council)
MEETING DATE:
MEETING TIME:
LOCATION:
Sepfember 13, 2000
6:00 P.M.
Tiburon Town Council Chambers
I. ROLL CALL
II. BUSINESS
A. BELVEDERE DRAINAGE DIVERSION PROJECT LANDSCAPING
1. LandscaDinl!: Plans
(a) Phase I (Approve Final Design/Plan)
(b) Phase n (Conceptual Review)
2. Wetlands Restoration (Information)
3. Maintenance & Irril!:ation
(a) Short Range Responsibility/Costs
(b) Long Range Responsibility/Costs
4. Phase I Cost Estimate & Fundinl!: Sources
5. Implementation Schedulerrimeline
III. ADJOURNMENT - to Regular Town Council Meeting, September20, 2000
DEPARTMENT:
General Administration
INITIATOR: Ed San Diego, City Manager
FOR COUNCIL
MEETING OF:
September 13, 2000
FINAL COUNCIL
DECISION BY: September 13, 2000
o CONSENT CALENDAR
o PUBLIC HEARING
~ OTHER SCHEDULED ITEM
o STATUS REPORT
o ORDINANCE
o RESOLUTION
o CONTRACT/AGREEMENT
o INFORMATION ONLY
o APPOINTMENTS
ITEM:
Approve recommended landscape plan for Reed Drainage Diversion Project
ATTACHMENTS:
None; the proposed landscape plans are too large to reproduce and will be available at the council meeting.
STAFF REPORT:
In response to concerns expressed about the scope of the landscaping that was to replace the vegetation removed to
accommodate the Reed Drainage Diversion system, Belvedere held a community-wide meeting on August I to
obtain input from the public regarding what should replace the landscape screening that existed between the multi-
use path and Tiburon Boulevard before work began on the project. Based on the input received, a committee
comprised of representatives from both Belvedere and Tiburon met with landscape architect Ralph Alexander on
four different occasions to develop a landscaping plan that will expand the plantings to provide the screening
desired. The plan that was developed by the committee, which it recommends approval of, calls for a two-phase
approach to landscaping and beautifying the area that was denuded.
PHASE I In Phase I, a total of359 different shrubs and trees would be planted in the area not controlled by
Caltrans, a drip irrigation system would be installed to service them, and the entire area would be
hydro-seeded upon completion to prevent erosion. The landscape architect informed the committee that the 182
myoporum shrubs to be planted will grow at a very fast rate to a height and width of 10-12 feet in two to three
years, thereby providing the desired screening as soon as possible. Irrigation for the plantings would be provided
from the City's well that also provides water to Tom Price Park and to the landscaping around the tennis courts on
Lagoon Road. Finally, additional mounding between the highway and the multi-use path is being done to help
increase the shielding of the pathway and the residents of Lagoon Road from Tiburon Boulevard traffic. The total
estimated cost of this portion of Phase I, which does not contemplate an ornamental landscaping approach, is
$89,552.
In addition to the above, the Army Corps of Engineers is requiring the City to reestablish the wetland area that
existed on the south-end of the project site, something that was not originally anticipated. The source of water for
this year-round wetland area was found to be a leak in the Marin Municipal Water District water main that runs
parallel to the drainage system that is being constructed and adjacent to the former wetland area. The leak has been
repaired and the seasonal wetland that will be created in its place calls for the planting of 1,454 2attails, various
wetland plants and trees. An irrigation system will be in installed to provide water to the 49 trees that will be
planted on the banks of the seasonal wetland area. The estimated cost of the wetland restoration portion of
Phase I is $29,000.
Both of the above cost estimates include the services of the landscape architect and the monitoring manual he will
develop for use by a biologist who must be engaged to monitor the seasonal wetland area. The costs also include
the maintenance ofthe irrigation system and all of the plants by the City until they are established (2-3 years), and
the services of the biologist mentioned above for 3 years. The total cost of Phase I is estimated to be $118,540.
Following is an itemized cost breakdown for Phase I:
continued. . .
STAFF RECOMMENDATION:
Approve Phase I landscaping project (including wetland restoration) and Phase II conceptually
ESTIMATED DISCUSSION TIME: 2 hours
AGENDA ITEM NO.:
Landscaping Staff Report
September 13,2000
Page 2
Phase I (Outside of Caltrans ril!ht-of-wav)
Medium Shrubs 5 gal. cans 182@$25
Myoporum Shrubs 5 gal. cans 152@$25
Trees 15 gal. cans 25@$150
Mounding & Grading (included in drainage diversion project costs)
Hydroseeding 55,302 sq. ft. @$.05
Drip Irrigation lump sum
Mobilization lump sum
Maintenance 3 Years@ $3,333/yr.
Su btotal
10% cont.
Su btotal
Prof Fees - Design (tIuu 9/15)
Prof Fees - Phase II Design (tIuu 9/15)
Prof Fees - Construction Drawings
Total
$
4,550
3,800
3,750
o
2,765
35,000
2,000
10,000
61,865
6,187
68,052
8,500
4,500
8,500
89,552
$
$
$
Wetland Restoration
Trees
Wetland Plants
Cattails
Irrigation
Maintenance - Included in Phase I
Mobilization - Included in Phase I
49@$25
1,096@$7.50
309@$15
lump sum
Subtotal
10% cont.
Subtotal
Prof. Fees - Design, Construction Drawings & Monitoring Manual
Monitoring by Biologist (3 years)
Total
$
1,225
8,220
4,635
2,500
o
o
16,580
1,658
18,238
6,250
4,500
28,988
$
$
$
$ 118,540
Grand Total - Phase I
PHASE II In addition to the work encompassed in Phase I, the Landscape Committee felt
that embellishments to the scope of work would be appropriate to consider,
providing funding could be raised to defray the cost of added plantings, irrigation and
maintenance. It is also predicated on approvals being obtained from Caltrans to use part of the
Tiburon Boulevard right-of-way. These embellishments are known as Phase II.
Phase II contemplates the planting of an additional 115 shrubs and trees in the Caltrans right-of-
way to further reduce the linear impact of the Phase I planting scheme, purchasing a water meter
to irrigate the expanded area (the City's well will not be able to support an irrigation system
beyond Phase I), and bringing in additional fill material to raise the height of the mound that
helps to deflect traffic sound from Tiburon Boulevard. It also includes 3 years of routine
maintenance for the plantings. Again, the approach is not to create an ornamental garden, but to
provide a more diverse green-belt between the multi-use path and the highway. The estimated
cost of this portion of Phase n is $76,875.
Should a more ornamental park-like approach be desired, Phase II include some options that call
for the planting of ground cover, more shrubs, and irrigation to provide year-round watering. In
addition, it would require the purchase of an additional allocation of water from MMWD (almost
another acre foot) and mulch for the expanded planting area. The estimated cost of the Phase
II options is $108,500. If everything is done in Phase n (options included), the total cost
rises to $185,375. Following is a cost breakdown of Phase II and the options:
Landscaping Staff Report
September 13, 2000
Page 3
PHASE II - Inside Caltrans Ril!ht-of -wav
Medium Shrubs 5 ga1.cans 75@$25 $ 1,875
Myoporum Shrubs 5 gal. cans 25@$25 625
Trees 15 gal. cans 15@$150 2,250
Irrigation lump sum 15,000
New Water Meter I 1/2" meter w/.25 ac. ft. 8,500
Mounding and Grading lump sum 25,000
Mobili7.ation lump sum 2,000
Maintenance - 3 years 6.000
Subtotal $ 61,250
10% cont. 6.125
Subtotal $ 73,375
Prof. Fees - Construction Drawings 3,500
Total $ 76,875
Options
Ground Cover Including Additional Irrigation lump sum $ 35,000
Additional plantings - shrubs - 5 gal. Cans lump sum 10,000
Mulch lump sum 20,000
Additional Water Supply Additional.95 ac. ft. 19,500
Additional Prof. Fees for above 8,000
Additional Maintenance - 3 years 16.000
Total $ 108,500
Grand Total - Phase II $ 185,375
FUNDING Funding for the above landscaping scenarios must be addressed. For Phase I, a
total of$95,000 has been identified thus far and it includes $55,000 in
City/Town funding, $20,000 from the Belvedere Community Foundation and the Tiburon
Peninsula Foundation in the form of$IO,OOO grants from each that are predicated on a dollar-for-
dollar match of contributions from the public (another $20,000). However, that leaves a
shortfall of approximately $23,500 that is necessary to fund all ofthe components of Phase I.
Following is a detailed breakdown of known anticipated available funding:
City of Belvedere
From diversion project contract $
FY2000/0 1 Budget
Town of Tiburon
Belvedere Community Foundation grant
Tiburon Peninsula Foundation grant
Public Contributions to match foundation grants
Total Known Anticipated Available Funding
25,000
20,000
$ 45,000
10,000
10,000
10,000
20,000
$ 95,000
The two Foundations have indicated that they will undertake the fundraising effort to raise the
private contributions for the grant matches. However, it is highly unlikely that all of the funding
necessary to defray the cost of the Phase I ($1 I 8, 540)--let alone the private contributions to
match the foundation grants--will be in-hand before the City is prepared to bid the landscaping
project. The two councils will have to decide if it is in the community's interest to front the
money necessary to cover the $23,500 shortfall and allow the project to proceed so the
planting can go in this winter. Staff would recommend that we do everything possible to
accomplish that goal.
With regard to Phase II, the two councils and the community will have to decide if it is desirable
to undertake the fundraising effort that will be necessary to raise $185,375 if everything is to be
done, or the $76,875 if just the plantings in the right-of-way are deemed sufficient.
Landscaping Staff Report
September 13, 2000
Page 4
IMPLEMENTATION PLAN If the two councils approve Phase I, the implementation
plan would entail having the landscape architect prepare
construction drawings, the City Engineer prepare bid documents, and the City putting the project
out to a fast-track public bid process. The actual schedule for the implementation will be
discussed at the joint meeting.
If it is deemed desirable to proceed with Phase II and any or all of the options, the actual work on
the construction drawings would only be done after a reasonable probability of the funds being
raised exists and Caltrans granting approval for an encroachment into its right-of-way appears
eminent.
Unfortunately, the project's landscape architect will not be able to attend the joint meeting
because of a conflict in his schedule. However, the City Engineer will lead the councils through
the landscape designs that have been prepared and exhaustively reviewed and subsequently
approved by the joint landscape committee.