RESOLUTION NO. 28- 2008
A RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF TIBURON
ACCEPTING THE MAR WEST STREET IMPROVEMENT PROJECT - PHASE] AND
AUTHORIZING THE FILING OF THE
NOTICE OF COMPLETION FOR THE WORK
WHEREAS, The Town Council budgeted funds in Fiscal Year 2007-200S to complete
the proj ect;
WHEREAS, Ghilotti Construction, Inc. was awarded the contract on August 15,2007 to
perform the work;
WHEREAS, The construction of the project was completed under budget on June 6,
200S;and
WHEREAS, The total final construction cost, including payment of total quantities
installed is $492,229.00.
NOW, THEREFORE, BE IT RESOLVED by the Town Council of the Town of
Tiburon as follows:
Section 1. The Town Council does hereby accept the construction of the Mar West Street
Overlay Improvement Project - Phase I as complete by Ghilotti Construction, Inc.
Section 2. The Town Council authorizes the Director of Public Works / Town Engineer to
execute the Notice of Completion and the Town Clerk to record the Notice of Completion.
Section 3. The Town Council authorizes the Director of Public Works / Town Engineer to
release the retention payment 35 days after the recordation date of the Notice of Completion,
pending release of any stop notices or Town claims.
PASSED AND ADOPTED at a regular meeting of the Town Council on the ISth day of
June, 200S, by the following vote, to wit:
AYES:
NOES:
ABSENT:
COUNCILMEMBERS:
COUNCILMEMBERS:
COUNCILMEMBERS:
Berger, Collins, Fredericks, Gram, Slavitz
None
None
ATTE~; / . /
/ "H /
j / C'~! 1 . / ,,'
, ~- ,'~. t{ J: -.. -'V!f
DIANE CRANE IACOPI, 'TOWN CLERK