HomeMy WebLinkAboutTC Res 2009-09-16 (3)RESOLUTION NO. 25-2009
A RESOLUTION OF THE TOWN COUNCIL
OF THE TOWN OF TIBURON ACCEPTING
THE ZELINSKY PLAYGROUND CONSTRUCTION PROJECT, AND
AUTHORIZING THE FILING OF THE NOTICE OF COMPLETION FOR THE WORK
WHEREAS, The Town Council budgeted funds in Fiscal Year 2008-2009 to complete
the project;
work; WHEREAS, P and J Utility was awarded the contract on April 15, 2009 to perform the
WHEREAS, the construction of the project was substantially completed within budget
on July 31, 2009; and
WHEREAS, the final construction cost, including payment of total quantities installed,
is $47,625.00.
NOW, THEREFORE, BE IT RESOLVED by the Town Council of the Town of
Tiburon as follows:
Section 1. The Town Council does hereby accept the Zelinsky Playground Construction
Project as complete by P and J Utility.
Section 2. The Town Council authorizes the Director of Public Works / Town Engineer to
execute the Notice of Completion and the Town Clerk to record the Notice of Completion.
Section 3. The Town Council authorizes the Director of Public Works / Town Engineer to
release the retention payment 35 days after the recordation date of the Notice of Completion,
pending release of any stop notices or Town claims.
PASSED AND ADOPTED at a regular meeting of the Town Council on the 16th day of
September, 2009, by the following vote, to wit:
AYES: COUNCILMEMBERS:
NOES: COUNCILMEMBERS:
ATTES
DIANE CRANE I PI, TOWN CLERK
BergeZlCollins, redericks, Gram, Slavitz
None ALICE FREDE
RICKS, MAYOR
TOWN OF TIBURON
1 /1