HomeMy WebLinkAboutTC Res 2010-01-20RESOLUTION NO. 08- 2010
A RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF TIBURON
ACCEPTING THE 2009 REED RANCH ROAD AND RIDGE ROAD OVERLAY
PROJECT (FEDERAL PROJECT NO. ESPL-5388-008),
AND AUTHORIZING THE FILING OF THE
NOTICE OF COMPLETION FOR THE WORK
WHEREAS, The Town Council budgeted funds in Fiscal Year 2009-2010 to complete
the project;
WHEREAS, North Bay Construction, Inc. was awarded the contract on September 2,
2009 to perform the work;
WHEREAS, The construction of the project was substantially completed under budget
on December 24, 2009; and
WHEREAS, The final construction cost, including payment of total quantities installed
is $294,678.
NOW, THEREFORE, BE IT RESOLVED by the Town Council of the Town of
Tiburon as follows:
Section 1. The Town Council does hereby accept the construction of the 2009 Reed Ranch
Road and Ridge Road Overlay Project (Federal Project No. ESPL-5388-008) as complete by
North Bay Construction, Inc.
Section 2. The Town Council authorizes the Director of Public Works / Town Engineer to
execute the Notice of Completion and the Town Clerk to record the Notice of Completion.
Section 3. The Town Council authorizes the Director of Public Works / Town Engineer to
release the retention payment 35 days after the recordation date of the Notice of Completion,
pending release of any stop notices or Town claims.
PASSED AND ADOPTED at a regular meeting of the Town Council on the 20th day of
January, 2010, by the following vote, to wit:
AYES:
COUNCILMEMBERS:
NOES:
COUNCILMEMBERS:
ABSENT:
COUNCILMEMBERS:
Collins, Fraser, Fredericks, O'Donnell, Slavitz
None
None
RICHARD COLLINS, MAYOR
TOWN OF TIBURON
1/2
ATTEST:;
DIANE CRANE IACOPI, TOWN CLERK
2/2